The kick off call of ENTSO-E IOP SDO 2012 was on 6 Feb 2012. The following main decisions were taken:
- Target to have frozen profile on 1 June 2012
- Target to have 1st stable release of the 2nd profile for IOP 2012 – 1 April 2012
- Validation tools – patch (CIMSpy/CIMdesk, …) available 2 weeks after
- Target to have 2nd stable release of the 2nd profile for IOP 2012 – 1 May 2012
- Validation tools – patch (CIMSpy/CIMdesk, …) available 2 weeks after
- Changes after 1 June should have minor corrective character
- Vendors should start to check the profile as of now, not after 1 June 2012
- Basic UML version for 2nd profile - CIM16-UML16v04 (versions will follow WG13 releases of CIM16 and EPRI projects deliverables)
- Weekly teleconferences will be organized: every Monday at 16:00h CET, starting from 20 Feb;
- The IOP date will be: the week of 9 July 2012 (the most preferred date among vendors) – 5 days IOP