Notes IOP call 21 May 2012
Review pending issues. A document was sent to WG13 for discussion during the physical meeting - end of May. The document can be find
here.
Aggreed on the change:
"according to the new profile a HydroPowerPlant must include at least one HydroPump. As you can see in the picture below, this is stated by cardinality 1…* on the highlighted association end near to HydroPump class.
But we think that there are real situations where a hydro plant doesn’t contain any hydro pump.
So the cardinality should be 0…*. On the other end of association our question is similar. In fact, we think that a hydro pump can exist only inside a hydro power plant.
So the relationship 0..1 should be changed to 1…1"
It should be noted that HVDC package can have further updates. Lars-Ola informed that IEC/TC22 is working on VSC and some coordination should be done. He expects to have more information for the WG13 meeting in US - end of May so that a direction to the HVDC model could be decided.
Dynamics package will need a couple of more itterations. The last two itesm of standard models are Load model and Wind model interconnections. Dynamics group is working to resolve these with the support of WG 13.
Participants: |
1 |
Frazzetta, Dario C… |
2 |
Zhu, Jun |
3 |
Martinovic, Lajos |
4 |
Cott, Giatgen |
5 |
Lopez, Rafael |
6 |
McMorran, Alan |
7 |
Pantea, Stefan |
8 |
Wiernowolski, Mich… |
9 |
Demaree, Kendall |
10 |
Rogowski, tomasz |
11 |
Ford, Michael |
12 |
Osterlund, Lars-Ol… |
13 |
Olsen, Svein |
14 |
falk, herb |